INDUSTRIES · TRANSMISSION

The outage is booked. One access trail isn’t cleared.

An outage window takes months to get and hours to lose. REALMS shows which structures are not ready while there is still time to do something about it.

Illustrative chart: four items are ready before the outage window; the access trail is late and not cleared.Illustrative chart: four items are ready before the outage window; the access trail is late and not cleared.
A BAD DAY ON A TRANSMISSION LINE

Everyone knew something. Nobody knew all of it.

Illustrative scenario.

01

Three weeks before

The land agent knows one landowner has not signed for the access trail to three structures. It is a row in her spreadsheet.

02

The week of the outage

Crews and equipment are staged. The schedule says the structures are ready.

03

The day

The crew cannot reach the structures. The outage runs out with the work undone, and the next window is months away.

WHAT IT COST

One late answer, paid for four ways.

The later you find out, the more it costs.

Three weeks early

A phone call and a change of sequence.

The week before

A scramble, and favours called in.

On the day

A crew and its equipment standing by.

After

The window, the relationship, and the argument about whose fault it was.

Schedule

Days lost first, then the window that was behind them.

Money

A crew and its equipment on standby. You know what a day of that costs you.

Reputation

With the contractor, the people whose land it is, and the board.

Approvals

Rushed work is how conditions get missed and approvals get put at risk.

WHY IT KEEPS HAPPENING

The information existed. It was in different hands.

The people working the approval knew

It was a line in a tracker built for their own team.

Construction had the schedule

Built from planned dates, not from what was cleared on the ground.

Nobody had both

No single record tied the access agreement to the structures the crew was about to work.

WHO KNOWS

Land

Access trail agreement: not signed.

Regulatory & permitting

Its own tracker, kept up to date.

Environment

Its own tracker, kept up to date.

Engineering & utilities

Its own tracker, kept up to date.

THE GAP

Nothing ties an approval to the ground it holds up.

WHO BUILDS

Planning

Builds the schedule from planned dates.

Construction

Mobilizes against the schedule.

Crews in the field

Find out when they get there.

WHO KNOWS / WHO BUILDS

Land

Access trail agreement: not signed.

Regulatory & permitting

Its own tracker, kept up to date.

Environment

Its own tracker, kept up to date.

Engineering & utilities

Its own tracker, kept up to date.

THE GAP

Nothing ties an approval to the ground it holds up.

Planning

Builds the schedule from planned dates.

Construction

Mobilizes against the schedule.

Crews in the field

Find out when they get there.

THE SAME DAY, WITH REALMS

Same project. Same problem. Known three weeks earlier.

01

Three weeks before

The access trail shows as Forecast Late, and the three structures behind it turn with it.

02

The decision

The construction manager sees what is held and why. Land gets help with the agreement, or the work is re-sequenced inside the window.

03

The day

The outage is used for the work it was booked for.

WHO KNOWS

Land

Access trail agreement: Forecast Late.

Regulatory & permitting

Its status lands on the location.

Environment

Its status lands on the location.

Engineering & utilities

Its status lands on the location.

ONE RECORD

Every approval tied to the ground it holds.

WHO BUILDS

Planning

Schedules the ground that is clear.

Construction

Moves crews to work that is ready.

Crews in the field

See what they can work today.

WHO KNOWS / WHO BUILDS

Land

Access trail agreement: Forecast Late.

Regulatory & permitting

Its status lands on the location.

Environment

Its status lands on the location.

Engineering & utilities

Its status lands on the location.

ONE RECORD

Every approval tied to the ground it holds.

Planning

Schedules the ground that is clear.

Construction

Moves crews to work that is ready.

Crews in the field

See what they can work today.

WHAT EACH LEADER GETS

One record. A different answer for each person who is accountable.

Executives

One readiness answer for the line, the reason behind it, and what is forecast to be late.

Construction managers

Which packages can go this week, and what is holding the rest.

Land & permitting leads

Every approval with an owner, a next step and a date, and a record of what was waiting on whom.

Project controls

A forecast date for every location, and a record of when each one was released to construction.

Indigenous & stakeholder relations

Every commitment on the ground it applies to, where crews will see it.

FOR IT

Built to sit inside your environment.

Your cloud or ours

Run REALMS in your own Azure tenant, or have us host it.

Your sign-in

Staff sign in with their Microsoft 365 accounts. No new passwords.

Your documents

Documents stay in your SharePoint.

Your data

A standard PostgreSQL database, open to your reporting tools through SQL or the REALMS API.

Your maps

Your ArcGIS layers on the same map as the project.

See REALMS on your line.

Bring the outage you are most worried about. We will show you what it depends on.